Summer Road Projects and Building Upgrades
When the road crews are in the area a notice will be posted. Building upgrades will bring the building into compliance for its size. The board is looking into the future for the building as well by including the groundwork for solar and generators. The board will be working on a building improvement plan and will budget accordingly.
Single chip seal over hard surface using 3/8 dark granite chip and hot oil
- Campbell Rd from 10th Ct to the end
- 11th Rd from CTH JJ to Cypress Rd
- 11th Rd from Cypress Rd to CTH II
- 9th Ave from Cottonville Ave to Chicago Dr
- Chicago Dr from 9th Ave to 8th Ln
- 8th Ln from Chicago Dr to town line
- Chicago Rd from CTH GG to 7th Ave
Cold mix overlay (wedging)
- 10th Ct to 11th Ave
Crackfilling
- Cottonville Ave from 9th to CTH B
- Chicago Rd from 7th Ave to CTH GG
Guardrails
- 9th Av bridge
Building Upgrades
- Install a new 320 amp pedestal
- Install 2- new 200 amp panels
- Add 2 new 200 amp automatic transfer switches for future generator
- Termination box for future solar array
- Install 2- new 110 cfm exhaust fans with timers vented to exterior if needed